Construction Begins - March, 2009
Road cones and construction equipment begin to appear on both sides of
I-43 and CTH W; north of STH 32 overpass; and south of STH 33 on-ramp:
   
Support Structures Under
Construction - April, 2009
The truss supports (green rebar and concrete box forms) begin to appear
along I-43 :
    
Support Structures Completed -
May, 2009
Box forms removed from
completed truss supports :
 
  
Deck Supports Installed -
Early June, 2009
Truss support constructed for
CTH W section:
Crane in-place for freespan
deck sections to be lifted onto truss supports (BIG LIFT -
June 17th):
    
    
Freespan Deck Installed - Late June, 2009
Deck sections installed over CTH W and I-43:
Work continues on both ends of bridge:
   
    |